Worlds First DTS installation in a Horizontal ICD Completion

Technical Background - Well Data

  • Location: Saudi Arabia.
  • Date: 2009.
  • Hole Size: 6 1/8”.
  • Well Type: Single lateral horizontal oil producer.

Project Objectives

  • Successfully install DTS in a ICD completion.
  • Determine inflow rate allocation to within 20% of PLT results. Tendeka Solution.
  • High resolution Sensornet DTS system.
  • FloQuest’s data interpretation services monitored the well during initial lateral multi-rate testing and PLT comparison.

Project Results

  • Results published in SPE paper SPE 122448 showing flow. contribution matches to within 20% of the PLT results, hence successful conclusion of the trial test.

Enquiry

Please get in touch, one of our experts will contact you to answer any questions.

Call us

We have a global network of offices:

North and South America
+1 832 827 4211

Europe, former Soviet Union, Sub-Saharan Africa
+44 1224 238 950

Middle East, North Africa
+44 1224 238 950

Asia Pacific
+603 9207 9797

Corporate HQ
+44 1224 238 950

Related Systems: